FusionModule500 Smart Mini Data Center
User Manual (ECC800e)
2.
Step 8 Install oblique beams as well as the beams in the front and rear and on the left and right based
on requirements.
Install antiseismic kits before and after the cabinet after connecting cables.
It is recommended that oblique beams as well as the beams in the front and rear and on the
left and right will not interfere with other devices.
The following figure shows the installation positions of the oblique beams as well as the
beams in the front and rear and on the left and right in a 42 U single cabinet scenario.
Issue 07 (2019-12-20)
Figure 2-20 Installing stiffeners at the bottom of the cabinet
Install a new door sill at the bottom of the cabinet.
Copyright © Huawei Technologies Co., Ltd.
2 Installation
40