Dali-gateway basic dg/s x.64.1.1
Hide thumbs Also See for i-bus KNX:
Table of Contents

Advertisement

®
ABB i-bus
KNX
Commissioning
Include in automatic duration/partial
duration test
Options:
Yes: The emergency lighting converter runs the automatic duration/partial duration test. The cycle
time for repeating the test can be set in the next parameter.
No: The emergency lighting converter does not run any automatic duration/partial duration tests.
The test can be explicitly triggered by an emergency lighting controller via one of the Trigger em
lighting test... group objects.
Yes
No
Selection of Yes option:
Dependent parameters:
Test cycle
Options:
1...52...97 weeks
This parameter defines the time interval that the emergency lighting converter uses to automatically
and cyclically run the duration/partial duration test.
Test mode
Options:
Duration test
Partial duration test
Duration and partial duration test
This parameter defines the type of emergency lighting test.
Duration test: The emergency lighting converter automatically starts a duration test. The start
of the test is executed at a fixed interval. The Test cycle parameter in this parameter window is
used to set the test cycle.
Partial duration test: The emergency lighting converter automatically starts a partial duration
test. The start of the test is executed at a fixed interval. The Test cycle parameter in this
parameter window is used to set the test cycle.
Note
The partial duration test is a duration test which is terminated by the gateway after the
partial duration test period. If there is no connection between the gateway and the
emergency lighting converter, it cannot stop the test once it has started. In such cases, the
emergency lighting battery fully discharges. The partial test becomes a full duration test.
Duration and partial duration test: The emergency lighting converter automatically starts a
partial duration or duration test. The start of the test is executed at a fixed interval. The Test
cycle parameter in this parameter window is used to set the test cycle. There is also a further
parameter that determines how often the test is a full duration test.