■2. 1:n connection of GOT and redundant system
(1) System configuration example
The following connection configuration examples are explained.
Control system
(system A)
N/W No.:1
PC No.:0
N/W No.:1
GOT
PC No.:4
(2) Connection method
Connect the CC-Link IE Field Network system to the GOT.
11. CC-Link IE FIELD NETWORK CONNECTION
(3) PLC Side Setting (GX Works3)
4.1.4 ■1. (3) PLC Side Setting (GX Works3)
(4) GOT Side Settings
Set GT Designer3 as follows.
Setting item
Controller Type
Device setting (Network setting)
MELSEC Redundant Setting
1) 2) 5)
4)
Ethernet cable
1)
Control system
(system A)
N/W No.:1
PC No.:2
1) Process CPU
2) Redundant function module
3) Tracking cable
4) CC-Link IE Filed Network Master/Local module (GOT connection)
5) CC-Link IE Filed Network Master/Local module (Remote I/O station connection)
MELSEC iQ-R, RnMT/NC
Host
NW No.: 1
Other
Station No.: Station number of the control system
The system (control system/standby system) of the the monitor target can
be speified.
Control system/
Only when checking [Enable Redundant Function] in the following
standby system
[MELSEC Redundant System Setting], [Control System/Standby System]
can be set.
4.3 MELSEC Redundant Setting
(Redundant system-1: Pair No.1)
1)
2)
5)
3)
2) 5)
4)
3)
Contents of setting
-
4.1 MELSEC iQ-R Series
Standby system
4)
(system B)
N/W No.:1
PC No.:1
(Redundant system-2: Pair No.2)
(Redundant system-2: Pair No.2)
1)
2) 5)
4)
Standby system
(system B)
N/W No.:1
PC No.:3
4
Model
4 - 21

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents