Epson C Series Maintenance Manual page 119

6-axis robots
Hide thumbs Also See for C Series:
Table of Contents

Advertisement

5. Fix the cross roller bearing's inner ring and the circular spline.
Hexagon socket head cap bolts: 4-M3×12
Tightening torque: 2.5 N·m (25 kgf·cm)
6. Grease the bearing of the wave generator and install it to the
shaft.
Hexagon socket set screws: 2-M4×5 (with a brass bushing)
Tightening torque: 2.5 N·m (25 kgf·cm)
When installing the wave generator, push it to the end and set
the set screws on the shaft's flat face.
For the other set screw, set the brass bushing to the end.
7. Install the removed bearing to the shaft.
8. Set the O-ring to the O-ring groove on the installation face of
the Arm #3 reduction gear unit.
C Series Maintenance Manual Rev.2
C4 Maintenance 7. Joint #3
O-ring
99

Advertisement

Table of Contents
loading

This manual is also suitable for:

C4

Table of Contents