C4 Maintenance 4. Cable Unit
53. Install the battery board.
Hexagon socket head cap bolts: 2-M3×8
Tightening torque: 0.7 ± 0.05 N·m
54. Install the connector to the battery board.
Connector: CN3
55. * If you are not replacing the battery relay cable, go to the step (56).
If replacing the battery relay cable:
Install the connectors to the battery unit.
Connector: BT (2 connectors)
(The connectors can be installed on either side)
56. Install the connectors to the battery board.
Connector: 2 connectors for the batteries, BT-CN1, BT-CN2, CN3
Wire tie: AB100
57. Install the control board 1 to the Arm #1 and connect the connector.
Cross recessed head screws: 3-M3×8
Tightening torque: 0.45 ± 0.1 N·m
Connector: GS01
58. Bind the cable protection spring (ø29, 130 mm) to the base cable
fixing plate.
Wire tie: AB100
Number of turns of spring to fix: 3 turns