Protocol selection
10.4.6
As shown in the setting menu for the Communication (Figure 10.4-11), the user should set
IEC103 for the [Slave Protocol] so that the communication in the IEC60870-5-103 standard is
carried out in the IED. Note that the restarting the IED (i.e., resetting the IED power) is
required after the user turns to the IEC60870-5-103 protocol.
Communication
10:48
1/3
LAN
>
USBCOM
>
SLAVE PROTOCOL
>
Figure 10.4-11 Slave protection for the IEC103 protocol (on IED setting menu)
Note: This sample menu illustrates how to select the IEC103, so that we do not discuss
the inclusion of IEC61850, DNP3.0, and Modbus and the selection of those
protocols here. See Figure 10.1-1 to check the inclusion of the protocols in the IED.
SLAVE PROTOCOL
10:48
1/1
Slave Protocol
+
IEC103
- 618 -
6F2S1931 (0.20)
SLAVE PROTOCOL
10:48
1/4
IEC61850†
IEC103
DNP3.0†
Modbus†
Centralized GRB200