4.2.1

Floor Mounting the CHS LARGE BATT BOX

1.
Use the template shown in
Guide on page 4-43
0.39" (10mm) anchor bolts (locally procured).
2.
Mark and drill the four holes required to install the CHS BASE
UNIT.
3.
Align bolt holes in CHS BASE UNIT (see
Mount Spacing Guide on page
and secure using four anchor bolts.
Because of injury from falling equipment, wall
mounting the CHS LARGE BATT BOX is not
recommended.
Mounting the CHS LARGE BATT BOX directly
on the floor is not recommended.
The CHS BASE UNIT raises the height of the
CHS LARGE BATT BOX 120mm (4.72").
When the CHS LARGE BATT BOX and
CHS2U-AU are connected for long term use,
the CHS2U JOINT BRACKET KIT is used.
Figure 4-57 Floor Mount Spacing
for required spacing before drilling holes for

Figure 4-57 Floor Mount Spacing Guide

4-43) with holes drilled in floor
Issue No. 1.5
Figure 4-57 Floor
4 - 43