Commissioning NC-controlled drives
6.3 Guided commissioning of SINAMICS drives
3. Accept the default setting of the line data or adjust the data to the power supply conditions
at the operating site.
4. Accept the default setting for the terminal wiring.
5. Check the configuration in the summary. Press the "Finish >" softkey to complete the
commissioning.
You can also save the configuration data in a text file.
6. Confirm the prompt with "Yes" to save the data to non-volatile memory.
7. Select "Cancel" to display the overview of the infeed: The two infeeds connected in parallel
are now commissioned.
126
CNC Commissioning: NC, PLC, Drive
Commissioning Manual, 12/2019, A5E48312804B AA