110
Equipment Installation
Install 19-Inch, 2-Post Rack Rail Kit
Step 6
Verify front and rear flanges on each bracket are installed in the correct rack position.
Step 7
Verify the installed brackets on the 19-inch, 2-post rack are spaced 440 mm apart and that brackets are level, as
shown in the following figure.
Note: Confirm the bracket spacing is correct at the front and rear of the rack. Use the bolts on the flanges to
adjust the spacing and tilt of the brackets.
Inner Width: 440 mm
Front View
Figure 35
Bracket Spacing 19-Inch, 2-Post Rack
Step 8
Tighten all bolts completely on each bracket.
Note: Each bracket is mounted to the rack using four bolts, two in the front and two in the rear.
Step 9
Tighten the flange nuts on both the left and right brackets, as shown in the following figure.
Note: Do not use excessive force to tighten the nuts.
·
Fujitsu and Fujitsu Customer Use Only
Release 19.1.1
Issue 1.1, May 2021