Initial System Turn Up

Provision L160 Tributary Blade

5.14
Provision L160 Tributary Blade
Note: The L160 Blade must be provisioned after provisioning the L100 Main blade ports and before provisioning
the L100 Main blade OTS interface.
Danger: L160 Raman blade emits very HIGH power light.
Danger: Never look into any ports of Raman blade directly. Never look into the end of a fiber, fiber cord,
or fiber pigtail connected with any ports of Raman blade. Permanent eye damage or blindness can occur
quickly when laser radiation is present.
Danger: Never expose bare skin to light from E1 port of Raman blade. Never bring bare hands near the
surface of the connector of E1 port and near the fiber which is connected with E1 port of Raman blade.
Danger: All ports and the surface of a fiber connector should be cleaned thoroughly. If dust exists on the
surface of a fiber connector or on the ports of Raman blade, it is burnt and melted due to the high power
light. The burning or melting action causes damage to the fiber connector or to the blade.
Figure 98
Clean and Damaged Fiber
Note: L100 Blade Issue 14, FC95453R11-I14, and later blade must be used with L160 Raman blade.
Step 1
Provision the L160 tributary blade.
Command:
% set eqpt shelf 101 type BDL1-3M21 shelf-mode NORMAL shelf-role TRIB admin-status
up
Step 2
Provision the Fan unit slots.
·
Release 19.1.1
Issue 1.1, May 2021
197
Fujitsu and Fujitsu Customer Use Only